题目

A company manufactures a single product L, for which the standard material cost is as follows.

                                                        $ per unit

Material 14 kg x $3                               42

During July, 800 units of L were manufactured, 12,000 kg of material were purchased for $33,600, of which 11,500 kg were issued to production.

SM Co values all inventory at standard cost.

What are the material price and usage variances for July?

A

Price                              Usage

$2,300 (F)                      $900 (A)

B

Price                      Usage

2,300 (F)                 $300 (A)

C

Price                       Usage

$2,400 (F)             $900 (A)

D

Price                       Usage

$2,400 (F)               $840 (A)

Chapter21Performancemeasurement

Since inventories are valued at standard cost, the material price variance is based on the materials purchased.

                                                                                                                $

12,000 kg material purchased should cost (x$3)                                36,000

but did cost                                                                                         33,600

Material price variance                                                                       2,400(F)

800  units manufactured should use (x 14 kg)                                   11,200 kg       

but did use                                                                                          11,500kg

Usage variance in kg                                                                           300kg(A)

x standard price per kg                                                                           x$3

Usage variance in                                                                               $900 (A)                     

多做几道

A company uses a standard absorption costing system. Last month budgeted production was 8,000 units and the standard fixed production overhead cost was $15 per unit. Actual production last month was 8,500 units and the actual fixed production overhead cost was $17 per unit.What was the total adverse fixed production overhead variance for last month?

A

$7,500

B

$16,000

C

$17,000

D

$24.500

A cost centre had an overhead absorption rate of $4.25 per machine hour, based on a budgeted activity level of 12,400 machine hours.In the period covered by the budget, actual machine hours worked were 2% more than the budgeted hours and the actual overhead expenditure incurred in the cost centre was $56,389.What was the total over or under absorption of overheads in the cost centre for the period?

A

$1,054 over absorbed

B

$2,635 under absorbed

C

$3,689 over absorbed

D

$3,689 under absorbed

Which of the following would help to explain a favourable direct labour efficiency variance?

(i) Employees were of a lower skill level than specified in the standard

(ii) Better quality material was easier to process

(iii) Suggestions for improved working methods were implemented during the period

A

(i), (ii) and (iii)

B

(i) and (ii) only

C

(ii) and (iii) only

D

(i) and(II) only

Which of the following statements is correct?

A

An adverse direct material cost variance will always be a combination of an adverse material price variance and an adverse material usage variance

B

An adverse direct material cost variance will always be a combination of an adverse material price variance and a favourable material usage variance

C

An adverse direct material cost variance can be a combination of a favourable material price variance and a favourable material usage variance

D

An adverse direct material cost variance can be a combination of a favourable material price variance and an adverse material usage variance

The following information relates to labour costs for the past month:

Budget                 Labour rate                      $10 per hour

                            Production time                15,000 hours

                           Time per unit                     3 hours

                           Production units                5,000 units 

Actual                Wages paid                       $176,000

                          Production                         5,500 units 

                        Total hours worked             14,000 hours

There was no idle time.

What were the labour rate and efficiency variances? 

A

Rate variance                 Efficiency variance

$26,000 Adverse           $25,000 Favourable

B

Rate variance                 Efficiency variance

 $26,000 Adverse           $10,000 Favourable

C

Rate variance                 Efficiency variance

 $36,000 Adverse           $2,500 Favourable

D

Rate variance                 Efficiency variance

 $36,000 Adverse           $25,000 Favourable